Contracting authority: MH ERS TREBINJE HIDROELEKTRANE NA DRINI AD · Roba se isporučuje i ugrađuje na adresi objekat Hidroelektrane na Drini, Nezuci bb, na paritetu DDP Višegrad, a za ino ponuđače na paritetu DAP Višegrad., Bosnia and Herzegovina
Estimated value
BAM 210,000
≈ €107,371 · CBBH peg middle rate on 14.05.2026
Submission deadline
10.03.2026 11:30 CET
closed 247 days ago
Description

The subject of the procurement is the delivery of a 20 kV distribution substation comprising five cells. Four cells are switchgear cells (two transformer bays and two line bays) and one metering cell. The procurement includes the supply, installation and commissioning of the substation.

Show source language

Predmet nabavke je isporuka razvodnog postrojenja nazivnog napona 20 kV, koje se sastoji od pet ćelija. Četiri ćelije su prekidačke (2 trafo polja i 2 dalekovodna polja) i jedna mjerna ćelija. Nabavka obuhvata isporuku, ugradnju i puštanje u rad postrojenja.

Details
Notice type
Contract award
Published
14.05.2026 08:58
External ID
ba_ejn-procedure-2644507
Procedure
Open procedure
Source
next.ejn.gov.ba
Same industry

Similar tenders

More like this →